Test on Work Breakdown Structure in Project Management
Work Breakdown Structure in Project Management: A Guide
Test: Work Breakdown Structure (WBS)
20 questions
Question 1: Under the Mission Analysis WBS element, activities related to program management are directly listed as sub-elements.
A. Yes
B. No
Explanation: The Mission Analysis WBS element (1.0) includes sub-elements such as Identify Projected Demand for Services, Identify Technological Opportunities, Identify Projected Supply of Services, and Mission Needs Analysis and Assessment. Program management is not listed as a direct sub-element under Mission Analysis in the provided materials.
Question 2: The WBS element for In-Service Management includes both Corrective Maintenance and Maintenance Control as distinct sub-elements.
A. Yes
B. No
Explanation: WBS Version 1.0 Page 13 shows that both 5.2 Corrective Maintenance and 5.4 Maintenance Control are listed directly under 5.0 In-Service Management.
Question 3: Is Environmental and Occupational Safety and Health Compliance a sub-element of WBS Element 3.0 Solution Development?
A. Yes
B. No
Explanation: Environmental and Occupational Safety and Health Compliance is a sub-element of WBS Element 4.0 Implementation, as indicated on WBS Version 1.0 Page 11.
Question 4: Initial Training is a sub-element of the same WBS Element (3.7 Support) that includes Support Equipment Acquisition / Modification.
A. Yes
B. No
Explanation: WBS Element 3.7 Support includes both 3.7.8 Initial Training and 3.7.5 Support Equipment Acquisition / Modification.
Question 5: Work Planning, Authorization and Management is a WBS element under 3.2 System Engineering.
A. Yes
B. No
Explanation: The WBS element 'Work Planning, Authorization and Management' is listed under 3.1 Program Management, not under 3.2 System Engineering.